The Productivity and Innovation Centre is a 190,000 square foot multipurpose building that houses advanced research and testing laboratories, space for small and medium-sized businesses, a dedicated hub for applied research activity along with administrative, teaching and service spaces. Designed and constructed through the use of a collaborative and integrated process, this steel and concrete framed building features innovative, sustainable and adaptable structural, mechanical and electrical systems. The building was conceived as two distinctive wings, each with their own unique structural system that was tailored to specific research functions. The single-story high head laboratory wing utilizes a steel frame system. While this appears conventional, a unique and innovative steel truss and girder solution was developed to simplify the installation and routing of the mechanical and electrical systems as well as provide future flexibility as the spaces are re-purposed over time.
NAIT Productivity & Innovation Centre

NAIT Productivity & Innovation Centre
Kerr Interior Systems Ltd.
NAIT Productivity & Innovation Centre
Edmonton, AB, Canada
5th Canadian Trophy Contestant

Key Challenges
- Very high standard from the architect
- Unique Spaces: industrial labs, small and large conference rooms, education spaces, large event spaces
- Large/high atrium
- Acoustical and fire security standards (ie. 2hr fire separation walls, with radius)

Key Challenges Cont.
- Large high elevation bulkheads and clouds with acoustical plaster finish
- Tight tolerance on visual aspect of ceiling finishes
- substantial coordination with other trades on sequencing to accommodate architectures standard
- Aggressive Schedule

Key Achievements
- KERR hosted our 40th Anniversary VIP celebration at this "showcase" facility (Nov. 2019)
- Building is targeted for LEED Gold Certification (exceed the project's mandate Silver Target)
- The building received the Award of Excellence at the Consulting Engineers of Alberta award gala.

Saint-Gobain Products & Systems
All CertainTeed Drywall (1/2" standard, 1/2" Type C, 5/8" Type X, Glasroc Shaftliner, Abuse Resistant, Diamondback Tile Backer, M2Tech Board - total board purchased 552,404 sft All CertainTeed "Lite" mud (compound) total mud purchase 1132 boxes