Antrim Gypsum Project News Archive
Community Liaison Committee (CLC) Update – First Meeting Completed
The first CLC meeting was held September 18, 2025, at the Bicentennial Theatre in Middle Musquodoboit. The meeting started with introductions and CertainTeed provided an update on what has happened with the Project since the public meetings in 2024. The updates had been posted on the Project Website:
https://www.certainteed.ca/antrim-gypsum-project
However, this discussion was more informal and involved some questions on future approvals needed and overall project schedule.
Some CLC members could not attend the first session due to other commitments or illness, but CertainTeed staff has reached out to those members to fill them in on the first meeting and confirm involvement going forward.
We discussed the following at the meeting and decided upon items by the CLC and Actions for CertainTeed are bolded:
- What is a CLC and how does it function?
CertainTeed staff gave an overview of the role of the CLC to be a voice for the communities that the Antrim Mine operates near including the mine, transport route and port facility. CertainTeed also outlined requirements in the Environmental Assessment (EA) Approval related to the CLC formation and operation. - Frequency of meetings - Once every two months for the first year or so with the next one after CertainTeed gets more information from Department of Highways - expected mid to late October so a CLC meeting in late October to early November is anticipated.
- Gypsum Transport Route - The route was outlined in the EA and is from an access point on Lake Egmont Road, north to the #224, east on the #224 to Upper Musquodoboit then south to Sheet Harbour port. CertainTeed is working with Department of Highways on road and bridge upgrades on Lake Egmont Road, but no details or schedule are worked out yet. See above.
- Update provided on the Active Trail project that was managed by Musquodoboit Valley Communities Association (MVCA), completed by Upland Planning and funded by CertainTeed. The project is looking at ways to get pedestrians and cyclists off the shoulder of the #224 from the High School to “the Square”. The report is being drafted and CertainTeed expects to see it by end of September and discuss it at next CLC.
Project Update – 1: Community Liaison Committee (CLC)
CertainTeed continues to seek members to serve on the CLC. Efforts through May and early June such as Public Notices, Project Website postings and direct reach outs to individuals did not yield the preferred number (7 to 9) of volunteers coming forward. CertainTeed will continue to work with local organizations and residents to get enough members so we can host a meeting as soon as possible but likely not until late summer or September. We appreciate all those volunteers that have expressed an interest to date and hope to move forward with the CLC as soon as we can to get this important community feedback mechanism in place.
Project Update – 2: Pre-construction Well Survey
CertainTeed would like to thank all the participants in the private residential well survey. Our consultant completing the work, GHD, is finishing the program this week and were able to get good representative coverage of the wells in the local area. The purpose of the survey was to understand how wells were constructed and current conditions of the wells before the Project is constructed. The data collected will be used to compare future groundwater quantity and quality conditions when the permitting of the project is complete, construction begins and further into operation and reclamation phases.
May 6, 2025
Project Updates – May 2025
- The Antrim Gypsum Project continues to progress through the advanced permitting stage towards operation. Activities over the past few months have included the following:
- Additional geotechnical drilling and test pitting to gather information for detailed mine design
- Continued environment monitoring (wetlands, surface water, groundwater and habitats) to supplement the two years of data already collected
- Advertising for the Community Liaison Committee (CLC) with a plan to have the CLC in place by June 2025
- Funding of an options analysis project being managed by the Musquodoboit Valley Communities Association and completed by Upland/Englobe for a multi-use trail in Middle Musquodoboit
- Upcoming planned activities include:
- Domestic well surveys close to the Project to establish baseline conditions
- Additional geotechnical drilling and well installations for groundwater and wetland monitoring
- Additional targeted surveys for Species At Risk to supplement existing knowledge to help with Management and Monitoring Plan development for the Industrial Approval applications
- Business owner and high school engagement sessions for the multi-use trail project
May 5, 2025
Community Liaison Committee (CLC) Update
The May 1st deadline for submitting an expression of interest for being a member of the CLC has passed. CertainTeed is reviewing candidates and will be reaching out via email or phone to confirm willingness of participants for this important linkage between the Project and local communities and businesses. CertainTeed hopes to be able to announce final members and have a first meeting in late May/early June. Thank you to all community members that expressed an interest in being part of the CLC. Individual circumstances change so there are often opportunities for new members to replace existing members of the CLC as the Project proceeds. CertainTeed will use the CLC and the Project website to communicate openings when they occur.
April 3, 2025
CertainTeed requesting expressions of interest for persons to serve on the Community Liaison Committee (CLC). See documents below for more information.
Call for Community Liasion Committee (CLC) Members
Community Liasion (CLC) Terms of Reference
February 14, 2025
CertainTeed has collaborated with the Musquodoboit Valley Communities Association (MVCA) to develop a Request for Proposals (RFP) for an Active Transportation Path Design. This initiative seeks to get conceptual designs and planning constraints identified for a trail that would provide safe passage from the High School to the town center area in Middle Musquodoboit for residents and visitors to use instead of the shoulder of Route #224. MVCA is the project lead and CertainTeed will assist with funding support. Please reach out via this project website to request further information.
February 12, 2025
During the months of February and March, there will be a continuation of limited activity on site including drilling and sampling for a geotechnical program, and installation of groundwater monitoring wells, as well as ongoing environmental monitoring. These activities include light trucks, a drill rig and field visits by staff to provide information for the permitting and detailed design of the project. If there are any questions or concerns that arise from these activities, please reach out via this project website.
Community Liaison Committee (CLC) Update – Second Meeting
The second CLC meeting was held November 27, 2025, at the Bicentennial Theatre in Middle Musquodoboit. An increase in the number of CLC members available for the second meeting versus the first was noted and appreciated by CertainTeed. The meeting started with introductions and CertainTeed provided an update on what has happened with the Project since the first CLC meeting on September 21, 2025. Project updates have been posted on the Project Website https://www.certainteed.ca/antrim-gypsum-project since the first CLC meeting as well. Some CLC members could not attend due to other commitments or illness, but CertainTeed staff will reach out to those members to fill them in on the second meeting.
We discussed the following at the meeting and actions for CertainTeed are bolded:
- Role of the CLC.
As some CLC members were attending their first meeting, CertainTeed staff gave an overview of the role of the CLC to be a voice for the communities that the Antrim Gypsum Mine operates near including the mine, transport route and port facility. CertainTeed also outlined requirements in the Environmental Assessment (EA) Approval related to the CLC formation and operation.
- CLC Members wanted an update on the overall permitting and development schedule.
Permitting - CertainTeed provided an overview of the permits that have been secured (Environmental Assessment Approval – October, 2024) and the ones needed (Industrial Approval – submitted this week and anticipated for Q1 or Q2, 2026) and the Fisheries Act Authorisation – in final draft, being reviewed by Mi’kmaq organizations and expected to be submitted before Christmas Break or January, 2026 to federal Department of Fisheries and Oceans and approval likely granted mid to late 2026).
Development – Many detailed engineering and planning activities are happening while permitting is ongoing. The site layout has been determined and equipment required for operation is being reviewed and finalized. With successful permitting noted above there may be some site activities such as road development, some site preparation (harvesting of merchantable wood, clearing and grubbing) in 2026. This initial development would be ramped up as permits are secured with the first gypsum going to the existing port facility in Sheet Harbour possible in 2027. The production level in that year likely being 25-50% of final production levels.
- CLC members wanted to discuss notification procedures for blasting, when required.
Currently it is expected that blasting will only be needed occasionally if hard rock is encountered that excavators, dozers and the surface miner can’t deal with. We discussed having a group text styled notification method for those closest to the mine and those that had sensitive receptors (livestock and persons sensitive to blast noises) were mentioned. CertainTeed committed to working directly with local residents and the CLC to have notification procedures in place before blasting happens that provide the maximum forewarning and details on blasting timing. - CLC members wanted to discuss the gypsum transport route and possible upgrades to roads and bridges.
The route was outlined in the EA and is from an access point on Lake Egmont Road near the current 1480 address, north to the #224, east on the #224 to Upper Musquodoboit then south to Sheet Harbour port. CertainTeed is working with Department of Highways on needed road and bridge upgrades on Lake Egmont Road. NSTPW indicated that road and bridge upgrades are in existing budgets. They are having design work done and scheduling meetings to determine what work could be completed in 2026 or 2027. CertainTeed has expressed an interest in having the work completed in 2026 so that incoming vehicles (staff, contractors, supplies) site development would be able to use the upgraded road/bridge. CertainTeed is scheduling further meetings with NSTPW and InvestNS to discuss timing and funding for the upgrades and will report back to the CLC on progress.
- Active Trail Project – Middle Musquodoboit
An update was provided by CertainTeed on the Active Trail project, managed by Musquodoboit Valley Communities Association (MVCA), completed by Upland Planning and funded by CertainTeed. The project is looking at ways to get pedestrians and cyclists off the shoulder of the #224 from the High School to “the Square”. CertainTeed is reviewing the final report and will provide a summary of results at the next CLC meeting.
- The CLC expressed an interest in knowing more about the reclamation plans for the site.
The reclamation process for the mine will be a “progressive reclamation” approach which is often described as “filling in the hole as you go”. There will be a net of material mined more than what will be moved to get to the gypsum so a lake will be present at the end of the project. The timing for the pit to naturally fill with water were calculated at roughly 10 years after all operations cease. Other reclamation activities like road removal, monitoring and revegetation programs in select areas would be happening while pit refilling happens. The final site needs to be safe, stable and fully vegetated in accordance with the Reclamation Plan before the Province returns all the reclamation bond monies.
- The CLC was interested in more information about the use of back-up beepers and tailgates on heavy equipment. The background is that they have observed or know of other operations where the sound can carry quite a distance and be an issue with sleep and livestock.
CertainTeed staff are familiar with these operational issues and provided information on the equipment, work schedule and approaches that will be used to minimize or eliminate these impacts. Back-up beepers on equipment will be used as required by provincial safety standards but operational hours (roughly 7am to 7 pm) should reduce impacts on sleep and occur when ambient noise is greatest (through daylight working hours). In some instances, the back-up beepers can be replaced with strobe lights if some mobile equipment is problematic for impacts to residents.
Tailgates on large mobile equipment (haul trucks) are not expected as the haul trucks will not be equipped with them. The haul trucks for taking gypsum to the port are side dump configured so will not have tailgates either. The on-site haul trucks will be an “open end dump” type truck. Some contractor equipment may have tailgates on equipment, but this is likely only during odd occasions during initial site development not during long term operations.
December 2, 2024
Over the winter months, you may see light vehicles and staff with high visibility clothing completing monitoring of groundwater wells and surface water locations. Heavier trucks and a drill rig may be observed as well through December to install more groundwater monitoring wells and collect geotechnical data on soils and bedrock. If there are any questions or concerns that arise from these activities, please reach out via this project website.
November 27, 2024
CertainTeed obtained environmental Assessment Approval on October 25, 2024, for the Antrim Gypsum Project. Many additional permits and approvals are needed before any construction activities occur. We will keep you updated on the permitting progress. Site activities that are allowable and help gather information for environmental management of the site include groundwater and surface water m